Timeline

  • June 2015: Choose site location
  • June 25, 2015: RFQ Architect Submittal due
  • June 29, 2015: Shortlisting of Architect Candidates
  • July 6, 2015: Interviews of Architect Candidates
  • July 13, 2015: Final selection of Architect
  • July – October 2015: Starion Sports Complex design process
  • July 29, 2015: Mandan Park Board Commissioners approved the Building Committee
  • July 29, 2015: Construction Manager at Risk was chosen (Northwest Contracting Inc.)
  • August 5, 2015: Weekly Design Consultant Meetings Begin with JLG
  • August 5, 2015: Weekly Owner Architect Contractor Meetings Begin with JLG
  • August 12, 2015: JLG meets with user group representatives on design specifics
  • October 2015: Increase in sales tax begins
  • December – January 2016: Design/development phase
  • January 2016: Bid the project
  • February – March 25, 2016: Construction document phase
  • March 8, 2016: Announce Naming Rights for the Sports Complex
  • March – April 2016: Award bids
  • April 2016: Construction begins
  • November 2016: Design and discussion on the Faris Field and current All Season Arena renovations
  • September 29, 2017: Completion of Starion Sports Complex
  • Fall 2017: Potential start of Faris Field and All Seasons Arena renovations