Timeline

  • June 2015: Choose site location

  • June 25, 2015: RFQ Architect Submittal due

  • June 29, 2015: Shortlisting of Architect Candidates

  • July 6, 2015: Interviews of Architect Candidates

  • July 13, 2015: Final selection of Architect

  • July – October 2015: Starion Sports Complex design process

  • July 29, 2015: Mandan Park Board Commissioners approved the Building Committee

  • July 29, 2015: Construction Manager at Risk was chosen (Northwest Contracting Inc.)

  • August 5, 2015: Weekly Design Consultant Meetings Begin with JLG

  • August 5, 2015: Weekly Owner Architect Contractor Meetings Begin with JLG

  • August 12, 2015: JLG meets with user group representatives on design specifics

  • October 2015: Increase in sales tax begins

  • December – January 2016: Design/development phase

  • January 2016: Bid the project

  • February – March 25, 2016: Construction document phase

  • March 8, 2016: Annouce Naming Rights for the Sports Complex

  • March - April 2016: Award bids

  • April 2016: Construction begins

  • November 2016: Design and discussion on the Faris Field and current All Season Arena renovations

  • September 2017: Completion of Starion Sports Complex

  • Fall 2017: Potential start of Faris Field and All Seasons Arena renovations