Timeline
- June 2015: Choose site location
- June 25, 2015: RFQ Architect Submittal due
- June 29, 2015: Shortlisting of Architect Candidates
- July 6, 2015: Interviews of Architect Candidates
- July 13, 2015: Final selection of Architect
- July – October 2015: Starion Sports Complex design process
- July 29, 2015: Mandan Park Board Commissioners approved the Building Committee
- July 29, 2015: Construction Manager at Risk was chosen (Northwest Contracting Inc.)
- August 5, 2015: Weekly Design Consultant Meetings Begin with JLG
- August 5, 2015: Weekly Owner Architect Contractor Meetings Begin with JLG
- August 12, 2015: JLG meets with user group representatives on design specifics
- October 2015: Increase in sales tax begins
- December – January 2016: Design/development phase
- January 2016: Bid the project
- February – March 25, 2016: Construction document phase
- March 8, 2016: Announce Naming Rights for the Sports Complex
- March – April 2016: Award bids
- April 2016: Construction begins
- November 2016: Design and discussion on the Faris Field and current All Season Arena renovations
- September 29, 2017: Completion of Starion Sports Complex
- Fall 2017: Potential start of Faris Field and All Seasons Arena renovations